# How to Read AI Compute Deals

> Source: https://aiwiki.ai/wiki/how_to_read_ai_compute_deals
> Updated: 2026-11-26
> Fact-checked: 2026-11-26
> Categories: AI Compute, AI Infrastructure, Data Centers
> License: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/) - attribute to "AI Wiki (aiwiki.ai)"
> Cite as: AI Wiki. "How to Read AI Compute Deals." aiwiki.ai, 26 Nov 2026. https://aiwiki.ai/wiki/how_to_read_ai_compute_deals
> From AI Wiki (https://aiwiki.ai), the free encyclopedia of artificial intelligence. Reuse freely with attribution.

A compute deal can reserve cloud resources, secure space and power for a data center, finance a build or support a lease. These arrangements can describe the same site and still measure different things. This guide follows what the parties said they signed, how they measured it, and when it becomes usable.[1][2][3]

## Find the agreement and its unit

| What to record | What to check |
|---|---|
| Parties and roles | Who will use the compute, build the site, sell the equipment or guarantee an obligation? |
| Type of agreement | Is it a lease, an order, a guarantee, an option, or an announced plan? |
| Capacity and unit | Does the figure measure utility power, critical IT load, accelerators, or work delivered? |
| Conditions and time | Is the next date a forecast, a contractual condition, a phase opening, or a report of use? |

In the PORTS-Pike disclosures, the parties distinguish power generation from IT capacity. OpenAI referred to electrical generation and grid work in describing the campus, and SB Energy's registration filing measures its leases in gigawatts of critical IT capacity. The numbers answer different questions about the same project.[1][2]

## Worked example: PORTS-Pike

| Disclosure | What it describes |
|---|---|
| About 8.0 GW of critical IT capacity | Seventeen executed leases between SB Energy subsidiaries and an OpenAI affiliate. The initial terms are 20 years from each applicable commencement date.[2] |
| First 800 MW expected in 2028 | OpenAI's announcement gave this as an expected first stage, with later stages subject to additional development. A target date describes expected delivery.[1] |
| About 4.25 GW and a $105 billion cap | The initial capacity covered by NVIDIA's residual value guarantees, and the aggregate cap on its payment obligation under those agreements. The cap is conditional exposure.[2][3] |

The 4.25 GW is part of the leased capacity, so adding it to 8.0 GW would count the same capacity twice. SB Energy says phase commencement depends on conditions that include power and interconnection availability and completion and commissioning of the buildings.[2]

## Look for operating evidence

A reporting company can provide operating evidence by identifying a cluster and saying it is being used. In its fourth-quarter 2025 results, Amazon described Project Rainier as operational, named the chip generation and said Anthropic was using the cluster for training.[4] Retain the date and attribution for each claim. The filing describes use of a particular cluster and gives no project-wide utilization figure.

For a record you can compare later, capture the announcement and filing dates, the actual agreement type, the relevant phase, and the latest evidence of use. The [list of AI compute deals](https://aiwiki.ai/wiki/list_of_ai_compute_deals) groups disclosed financings, leases, contracts and related arrangements.

## References

1. OpenAI. "OpenAI joins PORTS-Pike project." August 17, 2026. https://openai.com/index/openai-joins-ports-pike-project/
2. SB Energy. Form S-1/A, November 2026, PORTS-Pike Technology Campus leases. SEC EDGAR. https://www.sec.gov/Archives/edgar/data/2133037/000162828026075026/sbenergy-sx1a3.htm
3. NVIDIA. Form 8-K, August 17, 2026, Item 1.01. SEC EDGAR. https://www.sec.gov/Archives/edgar/data/1045810/000104581026000069/nvda-20260817.htm
4. Amazon. Fourth-quarter 2025 results, Exhibit 99.1. SEC EDGAR. https://www.sec.gov/Archives/edgar/data/1018724/000101872426000002/amzn-20251231xex991.htm