Nuclear power and AI
Nuclear power and AI refers to the use of nuclear fission (and, prospectively, fusion) to supply electricity to the data centers that train and run artificial intelligence systems, and to the wave of contracts that large technology companies signed with reactor owners and developers from 2023 onward. The deals fall into four groups: long-term purchases from operating reactors, restarts of reactors that had closed, capacity increases ("uprates") at existing plants, and agreements to buy power from small modular reactors and other advanced designs that have not yet been built. The best-known examples are Microsoft's 2024 agreement with Constellation Energy to restart Unit 1 at Three Mile Island, Amazon's purchase of a data center campus beside Talen Energy's Susquehanna plant, Google's order for a fleet of Kairos Power reactors, and Meta's January 2026 agreements for up to 6.6 GW of new and existing nuclear capacity [1][6][11][15]. Buyers describe nuclear as a firm, carbon-free supply for round-the-clock data center load [11][14]; critics point to the cost overruns and slow delivery of new reactors, and to the effect of diverting existing plants' output on other electricity customers and on emissions [7][28][29].
Background
Why AI companies turned to nuclear
A Lawrence Berkeley National Laboratory report released by the US Department of Energy in December 2024 found that US data centers used 58 TWh of electricity in 2014 and 176 TWh in 2023, about 4.4% of national consumption, and projected that they could account for roughly 6.7% to 12% of US electricity by 2028 [20]. The International Energy Agency's Energy and AI report, published in April 2025, estimated global data center consumption at about 415 TWh in 2024 and projected that it would more than double to around 945 TWh by 2030, with data centers responsible for almost half of the growth in US electricity demand over that period [21][22].
Several buyers tied the deals to their climate targets. Google tied its 2024 Kairos agreement to its goals of 24/7 carbon-free energy and net-zero emissions, and wrote that nuclear's round-the-clock output complements solar and wind [11]. Constellation said Microsoft would buy the restarted Three Mile Island unit's output as part of its goal to match the power its data centers in the PJM grid region use with carbon-free energy [1]. Meta described its December 2024 request for nuclear proposals as a way to obtain firm, baseload power for the grids serving its data centers, while noting that nuclear projects are more capital-intensive, slower to develop and more heavily regulated than solar or wind [14].
The IEA did not expect nuclear to carry most of the load. In its base case to 2035, half of the growth in data center demand is met by renewables, natural gas expands by 175 TWh (notably in the United States), and nuclear contributes about the same amount of additional generation as gas, mainly in China, Japan and the United States; the first small modular reactors come online around 2030 [22]. The IEA expected renewables and natural gas to lead in the near term because of their cost and availability in key markets [21].
Kinds of arrangement
| Type | How it works | Examples |
|---|---|---|
| Contract with an operating plant | Long-term power purchase agreement (PPA) for existing output, often tied to licence renewal | Meta and Clinton (Illinois), Amazon and Susquehanna (Pennsylvania), Meta and Vistra (Ohio) [8][9][15] |
| Restart of a closed reactor | Buyer's PPA finances refurbishment and relicensing of a shut unit | Microsoft and Crane (Three Mile Island Unit 1), Google and Duane Arnold (Iowa) [1][10] |
| Uprate | Contract pays for equipment changes that raise an existing reactor's output | Google and Constellation (890 MW), Amazon and Calvert Cliffs (about 190 MW) [26][27] |
| Co-location | Data center sits beside the plant and draws power directly | Amazon's Cumulus campus at Susquehanna [6][7] |
| New advanced reactors | Offtake agreement, equity investment or prepayment for plants not yet built | Google and Kairos Power, Amazon and X-energy, Meta and TerraPower or Oklo [11][13][15] |
| Fusion | Purchase agreement for a fusion plant still to be built | Microsoft and Helion, Google and Commonwealth Fusion Systems [18][19] |
Restarting closed reactors
Three Mile Island Unit 1 (Crane Clean Energy Center)
On September 20, 2024, Constellation Energy announced a 20-year PPA with Microsoft, the largest in Constellation's history, to restart Three Mile Island Unit 1 in Pennsylvania and rename it the Crane Clean Energy Center [1]. The unit, rated at about 835 MW, had been retired early for economic reasons in 2019; it is separate from Unit 2, which shut down after the 1979 accident [1]. Constellation's chief financial officer said the company would invest $1.6 billion in the restart through 2028, and CNBC reported at the time that Three Mile Island would be the second US nuclear plant to restart, after the Palisades plant in Michigan [2]. The original target was 2028; on the first anniversary of the announcement Constellation said the schedule had moved forward to 2027 after PJM accelerated approval of its interconnection request, and that the site was nearly 80% staffed [1][3].
The US Department of Energy closed a $1 billion loan to Constellation for the restart on November 18, 2025 [4]. In June 2026 the Nuclear Regulatory Commission (NRC) issued a draft environmental assessment and a draft finding of no significant impact for the restart, with a final restart decision expected in 2027 [5]. The NRC issued its final environmental assessment and finding of no significant impact in September 2026, and in November 2026 Constellation chief executive Joe Dominguez said the restart remained on track for the second half of 2027 [34].
Duane Arnold
In October 2025 Google and NextEra Energy announced a 25-year agreement under which Google will buy power from the Duane Arnold Energy Center in Iowa once it is restarted [10]. The 610 MWe boiling water reactor in Linn County began commercial operation in 1974 and stopped operating in 2020, after a severe storm in August of that year damaged its cooling towers; Google said it expected the plant to be back online in early 2029 and called restarting it "the fastest path to unlock large-scale nuclear power to meet AI growth in the near-term" [10]. The Central Iowa Power Cooperative, a minority owner, agreed to buy the rest of the output on the same terms [10].
Contracts with operating plants
Amazon and Susquehanna
In March 2024 Amazon Web Services agreed to buy Talen Energy's Cumulus data center campus, a 960 MW site next to the Susquehanna nuclear plant in Luzerne County, Pennsylvania, for a reported $650 million, with power to be supplied directly from the plant [6]. PJM Interconnection then filed an amended interconnection service agreement that would have raised the plant's behind-the-meter supply to the campus from 300 MW to 480 MW. On November 1, 2024 the Federal Energy Regulatory Commission (FERC) rejected it by a 2-1 vote, after the utilities American Electric Power and Exelon argued that the arrangement could shift up to $140 million a year in transmission costs onto other PJM customers [7]. Commissioner Mark Christie said that approval would set "a precedent that would be used to justify identical or similar arrangements in future cases", while Chairman Willie Phillips, dissenting, warned of risks to reliability and national security [7].
Talen restructured the deal in June 2025 as a 1,920 MW PPA running through 2042, worth about $18 billion over its life at full volume, under which the existing 300 MW co-located supply moves to a front-of-meter arrangement that Talen said does not need FERC approval [8]. Deliveries were scheduled to ramp from 840-1,200 MW in 2029 to 1,680-1,920 MW in 2032, and the companies agreed to explore uprates at Susquehanna and new small modular reactors in Pennsylvania [8].
Meta and Constellation's Clinton plant
In June 2025 Meta signed a 20-year agreement with Constellation for 1,121 MW from the Clinton Clean Energy Center in Illinois, starting in June 2027, plus 30 MW from an uprate [9]. The contract is meant to keep the plant running after an Illinois zero-emission credit program that supports it expires in 2027; Meta's head of global energy, Urvi Parekh, said that "Securing clean, reliable energy is necessary to continue advancing our AI ambitions" [9].
Meta, Vistra and the 2026 agreements
On January 9, 2026 Meta announced agreements that it said would support up to 6.6 GW of new and existing nuclear capacity by 2035 [15]. They comprise 20-year PPAs with Vistra for 2,176 MW from the Perry and Davis-Besse plants in Ohio, plus output from uprates at those plants and at Beaver Valley in Pennsylvania, for a total of 2,609 MW by 2034; funding for up to eight TerraPower Natrium reactors, the first two (up to 690 MW) as early as 2032; and support, including prepayment for power, for a 1.2 GW Oklo campus in Pike County, Ohio, whose first phase could come online as early as 2030 [15]. Meta's chief global affairs officer, Joel Kaplan, said that "Nuclear energy will help power our AI future" [15]. TerraPower began construction of its first Natrium plant in Kemmerer, Wyoming in April 2026 after receiving an NRC construction permit in March, with construction expected to finish in 2030 [32].
Uprates in 2026
On October 6, 2026 Constellation and Google announced a 20-year PPA supporting 890 MW of uprates at 11 reactors at six Constellation sites in Illinois, Pennsylvania and New Jersey, backed by $4.3 billion of Constellation investment, with the first uprate expected online in 2028 [26]. A separate 15-year agreement covers 2,700 MW from Constellation's existing PJM fleet and adds no new capacity, and a five-year technology agreement extends Constellation's use of Google Cloud and Gemini Enterprise [26][27]. About a week earlier Amazon had signed a 20-year PPA with Constellation for 690 MW from the 1,790 MW Calvert Cliffs plant in Maryland, including an uprate of about 190 MW expected between 2030 and 2032 and supporting more than $3 billion of investment and the relicensing of the two-unit plant [27]. POWER magazine also reported a Department of Energy conditional loan commitment of up to $4.2 billion for uprates and modernization at Vistra's Beaver Valley, Davis-Besse and Perry plants, which DOE said could add 433 MW, all of it under contract to Meta [27].
Small modular and advanced reactors
Google and Kairos Power
On October 14, 2024 Google signed what it called the "world's first corporate agreement to purchase nuclear energy from multiple small modular reactors", covering up to 500 MW from Kairos Power reactors, with the first unit targeted for 2030 and more through 2035 [11]. In August 2025 the Tennessee Valley Authority agreed to buy up to 50 MW from Kairos's Hermes 2 plant in Oak Ridge, Tennessee, for Google's data centers in Montgomery County, Tennessee and Jackson County, Alabama, with operation planned for 2030; Kairos said TVA was the first US utility to sign a PPA for electricity from a Generation IV reactor [12].
Amazon, X-energy and Dominion
On October 16, 2024 Amazon announced three agreements: support for four X-energy Xe-100 reactors (about 320 MW, expandable to about 960 MW) to be built by Energy Northwest near the Columbia Generating Station in Washington from the early 2030s; an investment in X-energy as part of a roughly $500 million funding round; and a memorandum of understanding with Dominion Energy aimed at developing a small modular reactor of at least 300 MW near the North Anna plant in Virginia [13]. Amazon and X-energy set a goal of more than 5 GW of new nuclear projects in the United States by 2039 [13]. The Xe-100 design received its first NRC construction permit in November 2026, after the NRC completed its safety review on October 30, for four 80 MWe units at Dow's Long Mott Generating Station in Seadrift, Texas, an industrial project rather than a data center; the permit does not authorise operation, and Dow had not yet made a final construction decision [33].
Oklo
Oklo, an advanced reactor developer whose board was chaired by OpenAI chief executive Sam Altman and which went public in May 2024 through a merger with Altman's special-purpose acquisition company, signed a non-binding master power agreement in December 2024 with the data center operator Switch for 12 GW of its Aurora powerhouses through 2044, and had earlier agreed a $25 million prepayment deal with Equinix for up to 500 MW [16][17]. Altman stepped down as chair on April 22, 2025, saying that as Oklo pursued partnerships "particularly to enable the deployment of AI, I believe now is the right time for me to step down"; CNBC reported that the move gave Oklo more freedom to explore partnerships with OpenAI or other hyperscalers [17]. Oklo's 1.2 GW Ohio campus for Meta followed in January 2026 [15].
Meta's request for proposals
Meta announced a request for proposals on December 3, 2024 for 1 to 4 GW of new US nuclear generation, to be delivered starting in the early 2030s, and said it wanted multiple units to reduce costs [14]. The TerraPower and Oklo agreements of January 2026 came out of that process [15].
Fusion agreements
Some AI companies have also signed contracts for power from fusion plants that have yet to be built. In May 2023 Helion Energy announced an agreement to supply Microsoft with electricity from a fusion plant expected online by 2028 and targeting 50 MW or more after a one-year ramp-up, with Constellation acting as power marketer [18]. In June 2025 Google agreed to buy 200 MW from Commonwealth Fusion Systems' first commercial plant, ARC, in Chesterfield, Virginia, alongside a second equity investment in the company [19].
Policy and regulation
US executive orders
On May 23, 2025 President Donald Trump signed four executive orders on nuclear energy [23]. According to the Department of Energy, they set a goal of expanding US nuclear capacity from about 100 GW to 400 GW by 2050, called for ten new large reactors with complete designs to be under construction by 2030, told the NRC to set an 18-month deadline for decisions on new construction and operating licenses, directed DOE to designate AI data centers as critical defense facilities and use its authorities to deploy advanced reactors to power them, and set a goal of three pilot test reactors reaching criticality by July 4, 2026 [23]. Under that pilot program, Antares Nuclear's Mark-0 microreactor completed a zero-power criticality demonstration at Idaho National Laboratory, reported on June 5, 2026 as the first to meet the deadline [24].
Co-location rules
The Susquehanna dispute turned co-location into a regulatory question for the PJM market. On December 18, 2025 FERC ordered PJM to write rules for co-locating data centers and other large loads at power plants, including three new transmission services, and said it would consider whether co-located load should pay a minimum charge toward the transmission system [25]. Analysts quoted by Utility Dive called the order a "major victory" for owners of nuclear and gas plants in PJM such as Constellation, PSEG and Vistra [25]. Constellation described its October 2026 Google agreement as a "direct response" to PJM's Bring Your Own Power proposal [26].
Industry pledges
At the CERAWeek conference in March 2025, Amazon, Google and Meta were among the companies that signed a World Nuclear Association pledge supporting a goal of tripling global nuclear capacity by 2050, known as the Large Energy Users Pledge [10][31].
Criticism and debate
Costs to other customers. The 2024 FERC case turned on whether co-located data centers would avoid paying for the transmission system they rely on, leaving those costs to other ratepayers [7]. A July 2025 Washington Post report said that technology companies were focusing on about two dozen operating plants in unregulated markets and that contracts with technology firms can offer plant owners as much as double the market rate, and that a Maryland Public Service Commission report had warned that diverting Calvert Cliffs' output to data centers could destabilize the grid [28].
Additionality. The Washington Post reported that by locking up existing plants instead of building new generation, technology companies could leave communities to fall back on fossil fuels, and that nuclear power redirected to them would in many cases be backfilled on the grid with gas or coal generation; Jackson Morris of the Natural Resources Defense Council said that tapping nuclear lets companies keep their carbon-free pledges but "doesn't do anything to solve for the impact they're having on consumers" [28]. Companies present restarts and uprates as additions: the Google and Constellation agreement, for example, was announced as supporting 890 MW of new nuclear generation [26].
Cost and schedule of new reactors. Recent US projects have run far over budget: the two new reactors at Vogtle in Georgia were expected to cost about twice their initial estimates, and two South Carolina reactors were cancelled after costs rose from $9.8 billion to $25 billion [29]. The first planned US small modular reactor project, NuScale Power's plant for Utah Associated Municipal Power Systems, was cancelled in November 2023 after its estimated power price rose from $58 to $89 per MWh and it could not attract enough utility subscribers [30]. Almost all advanced reactor deliveries in the agreements above are scheduled for 2030 or later, while the IEA expects renewables and gas to meet most new data center demand in the meantime [11][13][15][21].
Demand and safety. Henry Sokolski of the Nonproliferation Policy Education Center has argued that nuclear plants pay off over decades while AI electricity demand could fall if algorithms become more efficient, and former NRC commissioner Victor Gilinsky has warned that congressional pressure on the NRC to speed reviews trades safety for speed [29]. The same report noted Greenpeace's position that, although nuclear plants emit no carbon dioxide during generation, nuclear waste harms the environment [29].
Timeline
| Date | Event |
|---|---|
| 2023-05-10 | Helion announces fusion power agreement with Microsoft [18] |
| 2024-03 | AWS agrees to buy Talen's Cumulus campus at Susquehanna [6] |
| 2024-09-20 | Microsoft and Constellation announce Three Mile Island Unit 1 restart [1] |
| 2024-10-14 | Google and Kairos Power sign 500 MW fleet agreement [11] |
| 2024-10-16 | Amazon announces X-energy, Energy Northwest and Dominion agreements [13] |
| 2024-11-01 | FERC rejects expanded Susquehanna co-location agreement [7] |
| 2024-12-03 | Meta announces request for 1-4 GW of new nuclear [14] |
| 2024-12-18 | Oklo and Switch sign 12 GW non-binding agreement [16] |
| 2025-05-23 | Four US executive orders on nuclear energy [23] |
| 2025-06 | Meta signs Clinton PPA; Talen and Amazon sign 1,920 MW PPA [8][9] |
| 2025-06-30 | Google agrees to buy 200 MW from Commonwealth Fusion Systems [19] |
| 2025-08-18 | TVA, Google and Kairos sign Hermes 2 PPA [12] |
| 2025-10 | Google and NextEra announce Duane Arnold restart agreement [10] |
| 2025-11-18 | DOE closes $1 billion loan for Crane restart [4] |
| 2025-12-18 | FERC orders PJM to create co-location rules [25] |
| 2026-01-09 | Meta announces Vistra, TerraPower and Oklo agreements [15] |
| 2026-06-08 | NRC issues draft environmental assessment for Crane restart [5] |
| 2026-09 | NRC issues final environmental assessment for Crane restart [34] |
| 2026-09-30 | Amazon and Constellation announce Calvert Cliffs PPA [26][27] |
| 2026-10-06 | Google and Constellation announce 890 MW uprate agreement [26] |
| 2026-11 | NRC issues first Xe-100 construction permit (Long Mott, Texas) [33] |
Continue reading
- Data CenterA data center is a purpose-built facility, or a dedicated part of a facility, that houses and interconnects information technology and telecommunications equipment together with the power…Mentioned 19 times above
- Small Modular ReactorA small modular reactor (SMR) is a nuclear fission reactor with an electrical output of up to roughly 300 megawatts (MWe) per unit, about one third the capacity of a conventional gigawatt-class plant, whose…Mentioned 6 times above
- HyperscalerA hyperscaler is a company that builds and operates computing infrastructure at a scale far beyond a conventional enterprise IT estate: globally distributed fleets of data centers holding millions of servers…Listed in See also
- AI energy consumptionAI energy consumption is the electricity, and the associated water, land, and emissions, required to train and operate artificial intelligence systems, principally generative AI and large language models…Listed in See also
- Fermi AmericaFermi America is a United States power and data center developer attempting to build what it calls the world's largest energy and computing complexListed in See also
- Land, Power, and ShellLand, power, and shell (LPS) is an emerging commercial label for the physical site, deliverable electricity, and building structure needed before computing equipment can be installed in a large data center.Listed in See also
More to read
References
- ^1 ^2 ^3 ^4 ^5 ^6 ^7Constellation Energy. "Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid". Constellation Energy, September 20, 2024. constellationenergy.com/...-Free-Power-to-The-Grid
- ^Spencer Kimball. "Constellation Energy to restart Three Mile Island and sell the power to Microsoft". CNBC, September 20, 2024. cnbc.com/...island-and-sell-the-power-to-microsoft
- ^Constellation Energy. "One Year Later: Crane Clean Energy Center Still in the Spotlight and Ahead of Schedule". Constellation Energy, September 23, 2025. constellationenergy.com/...t-and-ahead-of-schedule
- ^1 ^2Ethan Howland. "DOE loans Constellation $1B to restart Three Mile Island nuclear unit". Utility Dive, November 19, 2025. utilitydive.com/...805923
- ^1 ^2ANS Nuclear Newswire. "NRC issues preliminary EA/FONSI for Crane restart". American Nuclear Society, June 9, 2026. ans.org/...s-preliminary-eafonsi-for-crane-restart
- ^1 ^2 ^3 ^4Rod Walton. "AWS Acquiring Hyperscale Data Center Directly Connected to Nuclear Plant". Microgrid Knowledge, March 5, 2024. microgridknowledge.com/...nnected-to-nuclear-plant
- ^1 ^2 ^3 ^4 ^5 ^6Ethan Howland. "FERC rejects interconnection pact for Talen-Amazon data center deal at nuclear plant". Utility Dive, November 4, 2024. utilitydive.com/...731841
- ^1 ^2 ^3 ^4Ethan Howland. "Talen to sell Amazon 1.9 GW from Susquehanna nuclear plant". Utility Dive, June 11, 2025. utilitydive.com/...750440
- ^1 ^2 ^3 ^4Lamar Johnson. "Meta, Constellation ink 20-year nuclear power deal to support AI goals". Utility Dive, June 6, 2025. utilitydive.com/...749992
- ^1 ^2 ^3 ^4 ^5 ^6World Nuclear News. "Duane Arnold restart underpins NextEra Energy and Google collaboration". World Nuclear News, October 28, 2025. world-nuclear-news.org/...and-google-collaboration
- ^1 ^2 ^3 ^4 ^5 ^6 ^7Michael Terrell. "Google signs advanced nuclear clean energy agreement with Kairos Power". Google (The Keyword), October 14, 2024. blog.google/...iros-power-nuclear-energy-agreement
- ^1 ^2Kairos Power. "Google, Kairos Power, TVA Collaborate to Meet America's Growing Energy Needs". Kairos Power, August 18, 2025. kairospower.com/...t-americas-growing-energy-needs
- ^1 ^2 ^3 ^4 ^5Brian Martucci. "Amazon announces small modular reactor deals with Dominion, X-energy, Energy Northwest". Utility Dive, October 16, 2024. utilitydive.com/...730022
- ^1 ^2 ^3 ^4Meta. "Accelerating the Next Wave of Nuclear to Power AI Innovation". Meta Sustainability, December 3, 2024. sustainability.atmeta.com/...o-power-ai-innovation
- ^1 ^2 ^3 ^4 ^5 ^6 ^7 ^8 ^9 ^10World Nuclear News. "Meta announces 'landmark' agreements for new nuclear". World Nuclear News, January 9, 2026. world-nuclear-news.org/...reements-for-new-nuclear
- ^1 ^2Sonal C. Patel. "Another Big Data Center Win for Nuclear: Oklo and Switch Sign Historic 12 GW Deal". POWER Magazine, December 18, 2024. powermag.com/...nd-switch-sign-historic-12-gw-deal
- ^1 ^2Pippa Stevens. "Sam Altman steps down as Oklo chair". CNBC, April 22, 2025. cnbc.com/...pany-up-to-work-with-more-ai-companies
- ^1 ^2 ^3Helion Energy. "Helion announces world's first fusion energy purchase agreement with Microsoft". Helion Energy, May 10, 2023. helionenergy.com/...irst-fusion-ppa-with-microsoft
- ^1 ^2 ^3Michael Terrell. "Our latest bet on a fusion-powered future". Google (The Keyword), June 30, 2025. blog.google/...test-bet-on-a-fusion-powered-future
- ^US Department of Energy. "DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers". US Department of Energy, December 20, 2024. energy.gov/...ease-electricity-demand-data-centers
- ^1 ^2 ^3International Energy Agency. "AI is set to drive surging electricity demand from data centres while offering the potential to transform how the energy sector works". IEA, April 10, 2025. iea.org/...o-transform-how-the-energy-sector-works
- ^1 ^2International Energy Agency. "Executive summary". Energy and AI, IEA, 2025. iea.org/...executive-summary
- ^1 ^2 ^3US Department of Energy, Office of Nuclear Energy. "9 Key Takeaways from President Trump's Executive Orders on Nuclear Energy". US Department of Energy, June 10, 2025. energy.gov/...umps-executive-orders-nuclear-energy
- ^World Nuclear News. "First criticality for US microreactor under DOE programme". World Nuclear News, June 5, 2026. world-nuclear-news.org/...ctor-under-doe-programme
- ^1 ^2 ^3Ethan Howland. "FERC orders PJM to craft large load colocation rules". Utility Dive, December 19, 2025. utilitydive.com/...808368
- ^1 ^2 ^3 ^4 ^5 ^6 ^7Robert Walton. "Constellation, Google strike 890-MW nuclear deal in PJM". Utility Dive, October 6, 2026. utilitydive.com/...832223
- ^1 ^2 ^3 ^4 ^5Sonal C. Patel. "Google Deal Backs 890 MW of Constellation Nuclear Uprates at 11 PJM Reactors". POWER Magazine, October 7, 2026. powermag.com/...nuclear-uprates-at-11-pjm-reactors
- ^1 ^2 ^3Evan Halper and Caroline O'Donovan. "Desperate for power, modern AI firms lean on a geriatric American nuclear fleet". The Washington Post, via Anchorage Daily News, July 30, 2025. adn.com/...n-on-a-geriatric-american-nuclear-fleet
- ^1 ^2 ^3 ^4Christopher White. "It's time to pump the brakes on talk of a mega nuclear energy buildout, experts warn". The National News Desk, via WLOS, January 17, 2025. wlos.com/...a-nuclear-energy-buildout-experts-warn
- ^Eric Wesoff. "Future of small reactors at stake as NuScale deal flops". Canary Media, November 9, 2023. canarymedia.com/...-at-stake-as-nuscale-deal-flops
- ^Jackson Walker. "Meta, Amazon among major tech companies pledging to triple nuclear energy capacity". The National News Desk, via KOKH, March 12, 2025. okcfox.com/...ng-to-triple-nuclear-energy-capacity
- ^ANS Nuclear Newswire. "TerraPower begins construction on Natrium power plant in Kemmerer". American Nuclear Society, April 24, 2026. ans.org/...tion-on-natrium-power-plant-in-kemmerer
- ^1 ^2World Nuclear News. "US issues landmark construction permit for Texas SMR plant". World Nuclear News, November 10, 2026. world-nuclear-news.org/...rmit-for-texas-smr-plant
- ^1 ^2ANS Nuclear Newswire. "Constellation Q3 updates: New Peak+, uprates, restart, midterm elections". American Nuclear Society, November 12, 2026. ans.org/...-peak-uprates-restart-midterm-elections
Improve this article
Add missing citations, update stale details, or write a clearer explanation. Anyone can edit: changes go live when you publish, and every edit is checked by an editor.
2 revisions · v2 · 4,102 words · full history
Fact-checks are independent of edits: a reviewer re-verifies the article against its sources and stamps the date. How we verify
Research and drafting on this wiki are AI-assisted, under named human editorial standards. How AI is used here
Reviewer note: Independent fact-check before publication on November 18, 2026: 112 claims checked against 35 cited and independent sources; 2 material and 10 minor corrections applied before publication.
Cite this page: AI Wiki. "Nuclear power and AI." aiwiki.ai, updated 18 Nov 2026, fact-checked 18 Nov 2026. CC BY 4.0. https://aiwiki.ai/wiki/nuclear_power